If it takes 4 workers 6 days to build a wall, how many days would it take 3 workers?
Dive into the world of maths magic! Every day, I will sprinkle your learning journey with 1 or 2 tantalizing questions from 11 plus Maths, GCSE Maths, and even thrilling Maths competitions. Gear up to conquer some of the most challenging brain-teasers in these realms. Let's make maths marvellous!
First, find the total amount of work needed to build the wall.
ReplyDelete4 workers × 6 days = 24 worker-days (This is the total work required to build the wall.)
Now divide the total work by the number of workers (3):
24 worker-days ÷ 3 workers = 8 days